Once a site has its MPAN or MPRN, everything that follows sits on the supply side and has a fixed order. The supplier appoints the metering agents, so no contract means no meter.
Verification
- Verified as at:
- Source:
- Omnium service levels; supplier and metering agent timescales vary
- Last reviewed by:
- Omnium
Figures in this sheet were current at the verification date above. Regulated charges reset each April. If you are relying on a figure, check the source or ask us.
A4 board pack. Cover page, then a running head and foot on every page.
The sequence
- Contract. The supply goes to market and a contract is agreed. Nothing downstream can start until this is done.
- Metering appointment. The supplier appoints the meter operator and data agents.
- Meter fit. The meter is installed and the supply energised.
What has to be ready on the day
The meter cannot be fitted into an unfinished position.
- Safe, permanent access to the meter position, with the site able to receive the engineer.
- The meter position itself complete: board, enclosure and any builder’s work finished.
- The correct isolation in place, and the incoming service terminated and live.
- Someone on site with authority to sign the work off.
A failed appointment costs the slot, not just the day. The next one is scheduled from the point of rebooking.
What we need from you
Site address and supply point number, the expected consumption and load, the legal entity taking the supply, and a contact who is actually on site.
The expected load matters more than people assume. A meter specified against the wrong load has to be changed later, at the site’s cost and on the metering agent’s timescale.
Where the delays come from
Almost always one of three things: the contract was not in place, so the metering appointment never started; the meter position was not ready on the day; or the entity taking the supply changed part way through and the contract had to be redone.
All three are avoidable and none of them are the meter operator’s fault.
Ask a question about this sheet
Ask about anything on this page and get an answer drawn from this sheet and the rest of the Knowledge series, with a link to the sheet it came from.
Hello, I'm Omnium's AI assistant. I can answer questions about business energy, our services and how we work, or put you in touch with the team. What can I help with?
This is an AI assistant. Answers come from published pages and are not a quotation, a contract, or legal, tax or financial advice. Questions are recorded so we can see what buyers are asking, and are covered by our privacy notice.
Read next
Where this leads
- Energy monitoring
Half-hourly data read and set against the site's operating pattern.
- Capacity (kVA) review
Agreed capacity tested against a full year of recorded demand.
The first review costs nothing. Anything after it is quoted and agreed in writing.
Supporting sheets in this series
- New connections
Getting a supply to a site that does not have one. The order the stages run in, and why the timescale is set by the network rather than by you.
Metering and data · verified 6 August 2026
- Meter types explained
Half-hourly, non-half-hourly, AMR, smart and unmetered supplies, what each means for billing and data, and why the meter type decides what you can see.
Metering and data · verified 6 August 2026
- Contract types, and how a fixed rate is built
The four business contract types, how a supplier assembles a fixed price, and why the wholesale market is no longer the larger part of an electricity rate.
Contracts and buying · verified 25 August 2026
Take this sheet into a meeting
New meter connections exports as an A4 board pack: a cover page carrying the title and the verification date, then the sheet itself with a running head and foot on every page.
If this sheet raises a question about your own sites, speak to us.